Planning and Time Management

<= Back * * * Next =>

Table of Contents

Theory

Planning

  1. Before planning, trainees should create their issues according to Issues Guide
  2. During planing team discus issues, corner cases and prepare plan for next iteration
Issues Guide
  1. Provide meaningful, descriptive name for the issue
    • NO any 'Exercise 1' or 'My article'
  2. Issue shouldn't have empty description, at least link to the 'source' of the issue
    • usually 'sources' of the issue somewhere in our content, for example you always can make a link to any exercise or theory subsection
    • put whatever useful information you may found to solve the issue
  3. Provide proper label for the issue
  4. Provide proper milestone, usually they like trainee-bootcamp, trainee-syntax etc
  5. Provide your estimation in some imaginary points, I call them elephants
  6. Don't hesitate to start discussion in comments section
    • for example it could be a question to mentor or some information to yourself
Labels
Label Description
theory Some media content which you have to read, watch or listen, usually they are items from Theory or Addition section
exercise Any exercise from Practice section
workshop Any cource or workshop which involves not only passive consuming of information but some actions from your side, like replicating of some actions. For example NodeSchool workshops
question Questions for some topic
project It's a special type of Practise, when you have to plan your project and split it into small sub-tasks
bug Defects in your exercise or project
tech-dept Bad design, code smells in your project
setup Installation or configuration of some software, tool etc
challenge Usually not simple task, require additional afford to complete
Estimation

My subjective recommendations

Points Description
1 Something trivial, it could takes you around one hour to make it done
2 Still clear what and how to do, may take from 1-2h to make it done
3 There are some minor unknown parts, you have to make some steps in learn/investigate things, it may takes you from 1-3h to make it done
5 Looks like investigation can take almost half of the time, you may spend around 4h to make it done
8 2/3 of you don't know, it can takes you around 6h to make it done
13 You have a clue on how to make it, but tasks seems challenging for you, it can takes whole day to make it done
20 It's a real challenge for you, so you are a bit scared by complexity of the task, however you desire to make it done, it can takes from one to three days of your time
40 Terra incognito, no lees then month of work
100 You are paralyzed by complexity of the task, you feel like it would takes years to make it done

⬆ back to top

Meetings

⬆ back to top

Time Management

  1. Each task has to be presented in our issue tracker
  2. Task has to be like "Do something in 5 hours" but not "Do something" (keep hours in your mind) in tracker use points
  3. Don't spend more time on the task then it requires
  4. Try to complete as much tasks as possible
  5. Write all completed actions and occurred problems. It would be ground for increasing time limit for the task
  6. Absence of time isn't a reason in cases like: "I was working on task A that's why haven't done task B". Exceptions are
    • dependent tasks, when incomplete A is a blocker for B.
  7. Try to work evenly. For example you have a task for 6 hour but delivery is in 3 days, it's ok to split for 2 hours per day. Work on few tasks simultaneously each day by combining complex and easy tasks
  8. Lear to effectively use time-frames for performing small sub-tasks. For example
    • build of the project
    • execution of tests
    • docs/email
  9. If you have done all urgent and important tasks for current iteration, take a look in future materials and try to prepare sketch plan for it, then go back for learned section and read additional materials like articles,books or bonus tasks.

⬆ back to top

Additional

  1. Time Management
  2. Software Estimation: How Misperceptions Mean We Almost Always Get It Wrong

Practice

Exercise 1

Prepare for next planning. Make sure that you cover all topics and assign proper labels and milestones. Don't forget about estimates. Prepare questions about exercises if any etc